Hi,
If I start defrag on a volume and while it is running, I try to run another maintenance task like balance or scrub: what will happen ? Doest it start the second task or it will wait for defrag to end before starting balance or scrub ?
Solved! Go to Solution.
Accepted Solutions
- Mark as New
- Bookmark
- Subscribe
- Subscribe to RSS Feed
- Permalink
- Report Inappropriate Content
Hello chopin70,
They are separate process, they can be enable all the same time. If you have large amount of data save on the NAS it will take a lot of resources for the NAS to run the processes and may affect the performance. We recommend to run the process one at a time.
Regards,
Marty_M
NETGEAR Community Team
All Replies
- Mark as New
- Bookmark
- Subscribe
- Subscribe to RSS Feed
- Permalink
- Report Inappropriate Content
Hello chopin70,
They are separate process, they can be enable all the same time. If you have large amount of data save on the NAS it will take a lot of resources for the NAS to run the processes and may affect the performance. We recommend to run the process one at a time.
Regards,
Marty_M
NETGEAR Community Team
- Mark as New
- Bookmark
- Subscribe
- Subscribe to RSS Feed
- Permalink
- Report Inappropriate Content
Re: Starting to maintenance jobs
Many thanks
Ideally, I would have imagined queing the tasks if we try to run them at same time as the performance impact makes it illogical to run both at same time
By the way: title was supposed to be: running two maintenance tasks...
I mistyped and forgot the W