I've bought a second RN102 for remote backup and trying to configure a new backup task.  I have followed the procedure outlined here:

 

https://kb.netgear.com/app/answers/detail/a_id/29741

 

However when I get to step 10 "Press Next" - nothing happens. "Test connection" passes, but it simply wont progress to the "Schedule" window for Step 11 of the process in the above instructions.

 

I've tried two different browsers (thinking it might be a glitch wit hone of them) but there is no difference.

 

NAS OS is 6.5.1

 

Is this a glitch with this latest update?  The only other time I've tried configuring backups was when I bought the first RN102 about 18 months ago, when I was backing up photos from USB sticks - which worked fine (they wouldn't have been scheduled to repeat, however)

 

Model: RN102|ReadyNAS 100 Series
Message 1 of 2

Accepted Solutions
basshead
Aspirant

Re: New Backup wont progress to Schedule window

I solved it..

 

"Host" was highlighted red.  I assumed the "Test" would've indicated it was incorrect.  I had a ":" after the host name; I removed it and it progressed to the Shedule window!

 

 

View solution in original post

Message 2 of 2

All Replies
basshead
Aspirant

Re: New Backup wont progress to Schedule window

I solved it..

 

"Host" was highlighted red.  I assumed the "Test" would've indicated it was incorrect.  I had a ":" after the host name; I removed it and it progressed to the Shedule window!

 

 

Message 2 of 2